Sprint end report
we have finished a sprint.
it would be nice to have a table overview
of stories and all tasks
- done/finished
- tasks started, but not finished
- pending for the next sprint
- estimated vs actual efforts
- estimated team velocity for this sprint
as a guideline for the next sprint
Statement from Kunagi Team
The report in the sprint history could be extended.
Created Story sto155 in Product Backlog.
Status
Issue is closed.
Comments
Wed, Nov 30, 2011, 06:47 by Ambar Shante
Risks, impediments, issues, qualities, etc. should also be integrated into this report. Or there should be an option to select what all information is to be shown in the report.
Ps: Could not post this comment under sto155. It gives the following message:
Failure
Posting your comment failed: HTTP Request identified as SPAM.