Estimation of very short Tasks

As a Team member I want to create very short Tasks to serve as plain reminders to do something, even if it takes only a minute. There is, however, no way to define Tasks that have an estimation lower than 1 hour.

Statement from Kunagi Team

Created Story sto216 in Product Backlog.

Status

Issue is closed.

Comments

Tue, Jul 3, 2012, 20:29 by Scott Adams

there is a way I think. There really are no units for the numbers in the tasks. So if you take them as minutes you can have a finer resolution!

Wed, Oct 17, 2012, 22:31 by Adam Martin

Sure you can take them as any measure, but it shows them as hours and this can throw off small tasks.

Thu, Oct 18, 2012, 00:46 by Scott Adams

Would certainly be nice if they were floating point instead of integer or at least fixed point with 1 decimal place :)