I am using kunagi, but like to know why product backlog items are moved out to sprint backlog instead of copying it. As a PO , i would like to have better view and performance reporting of PBI's
Status
Issue is closed.
Comments
Mon, Oct 3, 2011, 14:15 by artjom (PO,T)
You have to imagine an actual board of Stories that are physically moved from the Product Backlog (a project outline of all yet-to-implement features) to the Sprint Backlog (the short-term plan for the current iteration). Keeping all Stories in the PB would seriously encomber the clarity of the Product Backlog.
That being said, you can view summaries of the Sprint in the Sprint Backlog and the Sprint History views. Also, the Team's velocity is tracked and displayed within the Product Backlog view.