Feature Request:

Would like a Product BurnDown Chart at the top of the product page that maps Story Points Remaining vs Sprints (past and future (at current sprint length)). I would also like this chart to have a trend line from the current points remaining based on the rolling (3 sprint) average velocity. This would be helpful to Product owners to see when the remaining pointed stories could be completed based on the rolling average velocity.

New stories, or existing stories as they are pointed would add spikes to the chart for the sprint they were added. This would be acceptable behavior to me. I would expect this to resemble the Sprint Burndown chart in appearance.

Statement from Kunagi Team

See iss513.

Status

Issue is closed.