Story weirdness when kicking from / pulling to Sprint
To reproduce:
- create example project
- kick top two stories from sprint (first first, second second)
- switch to Product Backlog
Two things do not work as expected:
- the Story order is incorrect (second first, first second)
- the top Story cannot be pullted to Sprint (confirm estimation first, if necessary; selecting "Pull to Sprint" has no effect)
Statement from Kunagi Team
Cannot reproduce.
Status
Issue is closed for Release 0.23.
Comments
Thu, Mar 8, 2012, 15:17 by Witek (SM,T)
When kicking a story from sprint it always goes to the top of the PB. If you kick two stories, the second kicked is on the top. I think this is how it schould be.