Cannot pull stories in new sprint

Hello,

I filled product backlog and set the etsimated velocity to 80 but can only pull 4 storypoints into sprint backlog. Duration is set to 21 days started May25 and ending in June. Also in product backlog the issues fitting in the sprint was afetr the 4 pnts border.
Do I need a new Kunagi version? Known issue? What if all issues are solved in a sprint and I want to add more issues from product backlog? Is that possible

Statement from Kunagi Team

You have to set and confirm the estimation for a story to pull it into a sprint.

Team members always can pull new stories into a sprint.

Note that the estimated velocity has nothing to do with whether or not a Story can be pulled to the Sprint. It simply acts as a visual help for Sprint Planning.

Status

Issue is closed.

Comments

Wed, May 30, 2012, 13:04 by Witek (SM,T)

Do you get an error when trying to pull a story? Or is there no menu entry for pulling it?

Post a comment



optional