Display open Tasks in Product Backlog
To estimate Stories, which have been worked on in the last Sprint, it would be helpfull to see the corresponding open Tasks of the story.
Statement from Kunagi Team
Will not be implemented.
Estimation of Stories in Story Points should relative to other Stories in terms of complexity, not on the basis of implementation time estimation of specific operative Tasks that are concerned with the implementation.
We've had a lot of back and forth with Tasks. Currently, Tasks are removed after a Sprint ends. Stories need to be reestimated on the basis of current knowledge. The best thing is to use planning poker and its comparisons to other already estimated Stories.
Status
Issue is closed.