How do I move the special date out of sprint plan?

I need mark certain date as holiday, and all dev will not see the date from burndown chart

Status

Issue is closed.

Comments

Mon, Jun 18, 2012, 10:44 by Witek (SM,T)

Free days are not hidden because one can not guarantee that there is no burndown in practice on such days. Instead Kunagi adjusts the ideal burndown line and the future projection line.

For now it is only possible to mark specific weekdays as "free". This feature is not available for specific dates. But I could imagine this in future versions.

Mon, Jun 18, 2012, 22:42 by artjom (PO,T)

I'd like to point out that such a feature will propably not be in Kunagi before sto175 is done.